Project status

Project status

All approvals obtained, all stages completed by December 2024. Target for completion of works: December 2028.

COMPLETED

December 2024

All design, approval and permitting stages

FUNDING

May 2026

Signing of the European funding contract

TECHNICAL

June 2026

Preparation of technical documentation for tenders

TARGET

December 2028

Completion of execution works

Approvals & permits obtained

All documents from the competent authorities are valid.

  1. Technical-Economic Commission approval, Urban Planning Certificate stage — National Company Maritime Ports Administration Constanța.
  2. Issued by the Constanța City Hall, in accordance with the applicable urban planning legislation.
  3. Constanța Inspectorate for Emergency Situations approval — compliance with fire prevention and firefighting requirements.
  4. Environmental approval for implementing the project in the port area.
  5. Approval from the general designer of the Port of Constanța.
  6. Sanitary approval for the operation of the terminal.
  7. Ministry of National Defence approval — General Staff.
  8. Water management approval.
  9. Approval from the central authority in the field of transport.
  10. Building permit issued by the Constanța City Hall — all conditions met.